DOT/C/HW/155/09 - KHALIFA PORT INTERCHANGE - ABU DHABI
This project was a part of the massive development of Port Khalifa and the project was located in one of the busiest highway Sheikh Zayed Road/Sheikh Maktoum Road from Dubai to Abu Dhabi.The principal challenge was to execute thework without disrupting the heavy flow of traffic between Dubai & Abu Dhabi and maintaining 4 lines each for Dubai bound & Abu Dhabi bound.The safety requirement was a challenge and StructCon Constructions LLC has been executing the work to theclient’s satisfaction.
The project is ongoing and consists of post tensioned box girder bridges, voided slab underpasses, post tensioned deck on portal frame for traffic underneath.
The total no of bridges was 4 and 1 underpass.The total concrete quantitywas 17,230m3 and 4,480t of re bar.
Client: M/s. Dept. of Transport (DOT) - Abu Dhabi
|