PD/CA/BPS/AG/R21/P147-2014-DOT/14/026 IMPROVEMENT OF MAFRAQ TO AL GHWEIFAT BORDER POST HIGHWAY SECTION 3A; BAYNOUNAH FOREST TO AL MIRFA

This project is a very prestigious project in the Emirates of Abu Dhabi. Section 3A form a part of the "Improvement of Mafraq to Al Ghweifat Border Post Highway Section 3A; Baynounah Forest to Al Mirfa".

This project is a 300km plus expressway linking the Abu Dhabi Emirates to Saudi Arabia. Section 3A consists of 4 bridges, awarded to M/s. StructCon Constructions LLC, from Chainage 150 to Chainage 200.

All the bridges are post tensioned box girder, cast insitu. The project is a challenge in terms of working adjacent to a very busy live traffic throughout the day.

The total concrete in this project is 10,420m³ and 1,644 tons of rebar.

The project is ongoing and anticipated to complete by 3rd quarter of 2016.

Client: M/s. Musanada / Department of Transport-Abu Dhabi